Time
The duration needed to complete a stated quantity of work.
Notes for UPSC Principal & Vice-Principal examinations only.
Convert every worker or pipe into a fraction of the total task completed per unit time.
The duration needed to complete a stated quantity of work.
A complete job, chosen as \(1\) whole or a convenient number of units.
Work completed per unit time: fraction per day, units per hour, or tank per minute.
The speed of doing work. Greater efficiency means less time for the same task.
A daily rate cannot be added to an hourly rate. Convert first: if a worker completes \(\frac1{12}\) of a job per day in an \(8\)-hour day, the hourly rate is \(\frac1{96}\).
If A finishes in \(12\) days and B in \(18\) days:
Best when fractions remain simple.
Take total work as \(\operatorname{LCM}(12,18)=36\) units.
Best for joins, leaves, alternate days and wages.
For the same work and working conditions, doubling efficiency halves time.
If A takes \(12\) days and B takes \(18\) days, \(E_A:E_B=18:12=3:2\).
A \(25\%\) increase in efficiency gives \(T_2=T_1/1.25=0.8T_1\), a \(20\%\) time reduction.
| Situation | Combined rate | Time / inference |
|---|---|---|
| A takes \(x\), B takes \(y\) | \(\frac1x+\frac1y=\frac{x+y}{xy}\) | \(T=\frac{xy}{x+y}\) |
| A works; B destroys | \(\frac1x-\frac1y\), assuming \(x\lt y\) | \(T=\frac{xy}{y-x}\) |
| A+B take \(t\); A takes \(x\) | \(R_B=\frac1t-\frac1x\) | \(T_B=\frac{xt}{x-t}\) |
| Efficiency ratio \(a:b\) | Rates are \(a:b\) | Times are \(b:a\) |
| Same work, groups | \(M_1D_1E_1=M_2D_2E_2\) | When daily hours are equal. |
| Hours also vary | \(M_1D_1H_1E_1=M_2D_2H_2E_2\) | For the same quantity of work. |
A can finish a report in \(15\) days and B in \(10\) days.
Together they take \(6\) days.
A+B take \(8\) days; A alone takes \(12\) days.
B alone takes \(24\) days.
A is \(50\%\) more efficient than B. If B takes \(18\) days:
A takes \(12\) days.
If the net rate is positive, the tank fills. If it is negative, the tank empties. If it is zero, the level remains unchanged.
Pipes fill in \(12\) and \(18\) hours.
Both fill the tank in \(7\) h \(12\) min.
An inlet fills in \(8\) h; an outlet empties in \(12\) h.
With both open, the tank fills in \(24\) h.
A \(600\)-litre tank receives \(50\) L/min and loses \(20\) L/min.
Net discharge is \(30\) L/min.
Master join–leave patterns, alternate work, workforce equivalence, leaks and repeated cycles.
Break the schedule whenever the active team changes.
Never average the two rates unless the durations are equal and the question permits it.
A takes \(12\) days and B \(18\) days. They work together for \(4\) days; then A leaves.
Total elapsed time: \(12\) days.
If A and B work on alternate days, one complete \(2\)-day cycle produces:
Count full cycles, then assign the residual work to the person whose turn comes next.
A takes \(10\) days, B \(15\) days; A starts.
Five cycles complete \(\frac56\) in \(10\) days. A completes the last \(\frac16\) in \(\frac{5}{3}\) days.
Total: \(11\frac23\) days.
A “day” in the answer may be fractional unless the wording says work is performed only in whole-day shifts. Do not round automatically.
Let individual rates be \(a,b,c\). Then:
Individual rates:
A+B take \(12\) days, B+C \(15\) days, and C+A \(20\) days.
All three together finish in \(10\) days.
| Quantity | Meaning | How it affects output |
|---|---|---|
| \(M\) | Number of workers or equivalent workers | Directly proportional, if individual efficiency is unchanged. |
| \(D\) | Number of working days | Directly proportional. |
| \(H\) | Working hours per day | Directly proportional within the assumed range. |
| \(E\) | Efficiency per worker per hour | Directly proportional. |
| \(W\) | Quantity of work | Do not cancel when the two jobs differ in size. |
\(24\) workers, \(8\) h/day, finish in \(15\) days. Days for \(30\) workers at \(6\) h/day:
\(D=16\) days.
If the new job is \(k\) times the old work:
Never use equal-work cancellation when \(k\ne1\).
If \(x\%\) of workers leave and output must remain fixed, time multiplies by:
A \(20\%\) workforce fall increases time by \(25\%\).
If \(2\) skilled workers do as much work as \(3\) trainees:
A mixed team of \(8S+12T\) equals \(12T+12T=24T\).
If \(a\) workers of type X equal \(b\) workers of type Y:
The number ratio reverses to give the efficiency ratio.
Equal time means wages follow efficiency. Equal efficiency means wages follow time.
If hours per day differ, use total hours or include them separately.
Efficiencies A:B are \(3:2\). A works \(4\) days and B \(6\) days.
They receive equal shares.
For a \(20\%\) efficiency rise, time falls by \(\frac{2000}{120}=16\frac23\%\).
For a \(20\%\) efficiency fall, time rises by \(25\%\).
An inlet alone fills in \(x\) hours, but with a leak it takes \(y\) hours where \(y\gt x\).
A pipe fills in \(6\) h; with a leak, it takes \(8\) h.
The leak alone empties the full tank in \(24\) h.
If the inlet works alone for \(t_1\), then an outlet opens:
If inlet A runs for \(a\) minutes and outlet B for \(b\) minutes in every cycle:
Count full cycles, then analyse the remaining fraction in the exact order of the next cycle.
A fills in \(10\) h and B empties in \(15\) h. A runs for \(2\) h, then B for \(1\) h.
Seven cycles fill \(\frac{14}{15}\) in \(21\) h. A then fills \(\frac1{15}\) in \(\frac23\) h.
Total: \(21\frac23\) h.
Tank volume is proportional to water height.
Half the height means half the volume only for a uniform tank.
Use litres/minute or cubic metres/hour consistently.
If fraction \(f\) is already filled, remaining work is:
Do not calculate from an empty tank unless stated.
Protect accuracy when signs, schedules, efficiencies and units change.
Workers working together add rates, not completion times.
If time ratio is \(2:3\), efficiency ratio is \(3:2\).
An emptying pipe or leak has a negative rate while the tank is filling.
Convert hours to minutes or days to hours before combining rates.
Whenever someone joins or leaves, close the current phase and start a new rate.
The final fraction depends on whose turn begins the cycle and whose turn comes next.
Do not round a fractional finishing day unless work is restricted to completed shifts.
Men–days cancellation requires equal or explicitly adjusted efficiencies.
When daily working hours change, include \(H\) in the production equation.
If one job is larger, retain the work ratio \(W_1:W_2\).
Wages follow work contribution, which depends on both efficiency and duration.
Subtract rates \(\frac1x-\frac1y\), not hours \(y-x\).
A partly filled tank requires only the unfilled fraction.
If outlet capacity equals or exceeds inlet capacity, the tank will not fill.
Inverse variation makes the percentage changes unequal.
Average rates require correct time weights; phase calculation is safer.
For times \(x,y\), together time is \(\frac{xy}{x+y}\).
For positive time \(x\) and negative time \(y\), net time is \(\frac{xy}{y-x}\), with \(y\gt x\).
Choose total work as the LCM of individual times; rates become small integers.
Write time ratio, reverse it immediately, then label it efficiency.
Add the three pair rates and halve to obtain the rate of all three.
Efficiency rise \(x\%\) gives time fall \(\frac{100x}{100+x}\%\).
Calculate work per full cycle first; handle only the residual separately.
For wages, write \(E\times T\) under each worker, reduce the ratio, then divide money.
Adding help must reduce time; adding a leak must increase filling time.
Fix the total work, convert every agent to a signed rate, draw the schedule in phases, compute remaining work after each phase, and only then convert the final fraction into time.
Compact relationships for rapid revision.
Time is obtained only after the relevant work is divided by the net signed rate for that phase.