S4 · Topic 10 · Reasoning & Quant

Time & Work, Pipes & Cisterns

Notes for UPSC Principal & Vice-Principal examinations only.

01

The Foundation — Work Is a Rate Problem

Convert every worker or pipe into a fraction of the total task completed per unit time.

Basics

AThe four building blocks

Time

The duration needed to complete a stated quantity of work.

Work

A complete job, chosen as \(1\) whole or a convenient number of units.

Rate

Work completed per unit time: fraction per day, units per hour, or tank per minute.

Efficiency

The speed of doing work. Greater efficiency means less time for the same task.

BThe work–rate–time triangle

Universal relationship\[W=R\times T,\qquad R=\frac WT,\qquad T=\frac WR\]
  • If total work is taken as \(1\), a person finishing in \(x\) days has rate \(\frac1x\) work per day.
  • Rates of simultaneous helpers are added.
  • Rates of destroyers, leaks or outlets are subtracted.
  • All rates must use the same time unit.

Unit discipline

A daily rate cannot be added to an hourly rate. Convert first: if a worker completes \(\frac1{12}\) of a job per day in an \(8\)-hour day, the hourly rate is \(\frac1{96}\).

CTwo valid models: unit fraction and LCM work

Model 1 — Total work \(=1\)

If A finishes in \(12\) days and B in \(18\) days:

\[R_A=\frac1{12},\quad R_B=\frac1{18}\]\[R_{A+B}=\frac1{12}+\frac1{18}=\frac5{36}\]
\[T_{A+B}=\frac1{5/36}=\frac{36}{5}=7\frac15\text{ days}\]

Best when fractions remain simple.

Model 2 — LCM total work

Take total work as \(\operatorname{LCM}(12,18)=36\) units.

\[E_A=\frac{36}{12}=3\text{ units/day},\quad E_B=\frac{36}{18}=2\text{ units/day}\]
\[T_{A+B}=\frac{36}{3+2}=\frac{36}{5}\text{ days}\]

Best for joins, leaves, alternate days and wages.

1. List times\(12,18\)
2. Take LCM\(36\) units
3. Find rates\(3,2\)
4. Apply scheduleAdd/subtract units
5. DivideWork ÷ rate

DEfficiency and time are inversely proportional

Inverse relation

\[E\propto\frac1T,\qquad E_1T_1=E_2T_2\]

For the same work and working conditions, doubling efficiency halves time.

Efficiency ratio from time

\[E_A:E_B=T_B:T_A\]

If A takes \(12\) days and B takes \(18\) days, \(E_A:E_B=18:12=3:2\).

Time after efficiency change

\[T_2=T_1\frac{E_1}{E_2}\]

A \(25\%\) increase in efficiency gives \(T_2=T_1/1.25=0.8T_1\), a \(20\%\) time reduction.

ECore team formulas

SituationCombined rateTime / inference
A takes \(x\), B takes \(y\)\(\frac1x+\frac1y=\frac{x+y}{xy}\)\(T=\frac{xy}{x+y}\)
A works; B destroys\(\frac1x-\frac1y\), assuming \(x\lt y\)\(T=\frac{xy}{y-x}\)
A+B take \(t\); A takes \(x\)\(R_B=\frac1t-\frac1x\)\(T_B=\frac{xt}{x-t}\)
Efficiency ratio \(a:b\)Rates are \(a:b\)Times are \(b:a\)
Same work, groups\(M_1D_1E_1=M_2D_2E_2\)When daily hours are equal.
Hours also vary\(M_1D_1H_1E_1=M_2D_2H_2E_2\)For the same quantity of work.

Combined work

A can finish a report in \(15\) days and B in \(10\) days.

\[T=\frac{15\times10}{15+10}=6\text{ days}\]

Together they take \(6\) days.

Find the unknown worker

A+B take \(8\) days; A alone takes \(12\) days.

\[R_B=\frac18-\frac1{12}=\frac1{24}\]

B alone takes \(24\) days.

Different efficiencies

A is \(50\%\) more efficient than B. If B takes \(18\) days:

\[E_A:E_B=3:2\Rightarrow T_A:T_B=2:3\]

A takes \(12\) days.

FPipes and cisterns: the same mathematics with signs

Filling pipePositive rate
Emptying pipeNegative rate
Full tankWork \(=1\)
Net tank rate\[R_{\text{net}}=\sum R_{\text{inlets}}-\sum R_{\text{outlets}}\]

If the net rate is positive, the tank fills. If it is negative, the tank empties. If it is zero, the level remains unchanged.

Two inlet pipes

Pipes fill in \(12\) and \(18\) hours.

\[T=\frac{12\times18}{12+18}=\frac{36}{5}=7\frac15\text{ h}\]

Both fill the tank in \(7\) h \(12\) min.

Inlet and outlet

An inlet fills in \(8\) h; an outlet empties in \(12\) h.

\[R=\frac18-\frac1{12}=\frac1{24}\]

With both open, the tank fills in \(24\) h.

Capacity form

A \(600\)-litre tank receives \(50\) L/min and loses \(20\) L/min.

\[T=\frac{600}{50-20}=20\text{ min}\]

Net discharge is \(30\) L/min.

02

The Deep Dive — Schedules, Groups and Variable Rates

Master join–leave patterns, alternate work, workforce equivalence, leaks and repeated cycles.

Expert

AWhen workers join or leave

Phase method

Break the schedule whenever the active team changes.

\[W_1=R_1T_1,\qquad W_{\text{left}}=W-W_1\]\[T_2=\frac{W_{\text{left}}}{R_2}\]

Never average the two rates unless the durations are equal and the question permits it.

A leaves after some days

A takes \(12\) days and B \(18\) days. They work together for \(4\) days; then A leaves.

\[W_1=4\left(\frac1{12}+\frac1{18}\right)=\frac59\]\[W_{\text{left}}=\frac49,\quad T_B=\frac{4/9}{1/18}=8\text{ days}\]

Total elapsed time: \(12\) days.

StartA + B begin
Phase 1Use \(R_A+R_B\)
Change pointA leaves
Phase 2Use \(R_B\)
FinishAdd phase times

BAlternate-day and repeating schedules

Cycle principle

If A and B work on alternate days, one complete \(2\)-day cycle produces:

\[W_{\text{cycle}}=R_A+R_B\]

Count full cycles, then assign the residual work to the person whose turn comes next.

Alternate days

A takes \(10\) days, B \(15\) days; A starts.

\[W_{2\text{ days}}=\frac1{10}+\frac1{15}=\frac16\]

Five cycles complete \(\frac56\) in \(10\) days. A completes the last \(\frac16\) in \(\frac{5}{3}\) days.

Total: \(11\frac23\) days.

Last partial day

A “day” in the answer may be fractional unless the wording says work is performed only in whole-day shifts. Do not round automatically.

\[T_{\text{last}}=\frac{W_{\text{remaining}}}{R_{\text{next}}}\]

CPairwise team data

Given pair rates

Let individual rates be \(a,b,c\). Then:

\[a+b=p,\qquad b+c=q,\qquad c+a=r\]
\[a+b+c=\frac{p+q+r}{2}\]

Individual rates:

\[a=\frac{p+r-q}{2},\quad b=\frac{p+q-r}{2},\quad c=\frac{q+r-p}{2}\]

Three-team reconstruction

A+B take \(12\) days, B+C \(15\) days, and C+A \(20\) days.

\[a+b+c=\frac12\left(\frac1{12}+\frac1{15}+\frac1{20}\right)=\frac1{10}\]

All three together finish in \(10\) days.

DMen–days–hours–efficiency model

General production model\[W\propto M\times D\times H\times E\]\[\frac{W_1}{W_2}=\frac{M_1D_1H_1E_1}{M_2D_2H_2E_2}\]
QuantityMeaningHow it affects output
\(M\)Number of workers or equivalent workersDirectly proportional, if individual efficiency is unchanged.
\(D\)Number of working daysDirectly proportional.
\(H\)Working hours per dayDirectly proportional within the assumed range.
\(E\)Efficiency per worker per hourDirectly proportional.
\(W\)Quantity of workDo not cancel when the two jobs differ in size.

Changed workforce and hours

\(24\) workers, \(8\) h/day, finish in \(15\) days. Days for \(30\) workers at \(6\) h/day:

\[24\times15\times8=30\times D\times6\]

\(D=16\) days.

More work too

If the new job is \(k\) times the old work:

\[\frac{M_1D_1H_1E_1}{M_2D_2H_2E_2}=\frac{W_1}{W_2}=\frac1k\]

Never use equal-work cancellation when \(k\ne1\).

Workforce reduction

If \(x\%\) of workers leave and output must remain fixed, time multiplies by:

\[\frac{100}{100-x}\]

A \(20\%\) workforce fall increases time by \(25\%\).

EEquivalent workers: men, women, machines or teams

Convert to one common unit

If \(2\) skilled workers do as much work as \(3\) trainees:

\[2S=3T\Rightarrow 1S=\frac32T\]

A mixed team of \(8S+12T\) equals \(12T+12T=24T\).

Efficiency from stated equivalence

If \(a\) workers of type X equal \(b\) workers of type Y:

\[aE_X=bE_Y\Rightarrow E_X:E_Y=b:a\]

The number ratio reverses to give the efficiency ratio.

FWork and wages

Basic rule

\[\text{Wage share}\propto\text{work done}=E\times T\]

Equal time means wages follow efficiency. Equal efficiency means wages follow time.

General wage ratio

\[W_A:W_B=E_AT_A:E_BT_B\]

If hours per day differ, use total hours or include them separately.

Unequal time

Efficiencies A:B are \(3:2\). A works \(4\) days and B \(6\) days.

\[W_A:W_B=(3\times4):(2\times6)=1:1\]

They receive equal shares.

GEfficiency change and time change are not equal percentages

Efficiency rises by \(x\%\)

\[\text{Time fall}=\frac{100x}{100+x}\%\]

For a \(20\%\) efficiency rise, time falls by \(\frac{2000}{120}=16\frac23\%\).

Efficiency falls by \(x\%\)

\[\text{Time rise}=\frac{100x}{100-x}\%\]

For a \(20\%\) efficiency fall, time rises by \(25\%\).

HLeaks, delayed outlets and observed-time problems

Find a hidden leak

An inlet alone fills in \(x\) hours, but with a leak it takes \(y\) hours where \(y\gt x\).

\[R_L=\frac1x-\frac1y\]
\[T_L=\frac{xy}{y-x}\]

Leak capacity

A pipe fills in \(6\) h; with a leak, it takes \(8\) h.

\[R_L=\frac16-\frac18=\frac1{24}\]

The leak alone empties the full tank in \(24\) h.

Outlet opened later

If the inlet works alone for \(t_1\), then an outlet opens:

\[W_1=\frac{t_1}{x},\quad W_{\text{left}}=1-W_1\]\[T_2=\frac{W_{\text{left}}}{1/x-1/y}\]

IRepeated opening cycles

Cycle-rate method

If inlet A runs for \(a\) minutes and outlet B for \(b\) minutes in every cycle:

\[W_{\text{cycle}}=\frac a{x}-\frac b{y},\qquad T_{\text{cycle}}=a+b\]

Count full cycles, then analyse the remaining fraction in the exact order of the next cycle.

Alternating pipe schedule

A fills in \(10\) h and B empties in \(15\) h. A runs for \(2\) h, then B for \(1\) h.

\[W_{3\text{ h cycle}}=\frac2{10}-\frac1{15}=\frac2{15}\]

Seven cycles fill \(\frac{14}{15}\) in \(21\) h. A then fills \(\frac1{15}\) in \(\frac23\) h.

Total: \(21\frac23\) h.

JTank volume and level

Uniform cross-section

Tank volume is proportional to water height.

\[\frac{V_1}{V_2}=\frac{h_1}{h_2}\]

Half the height means half the volume only for a uniform tank.

Known capacity

\[T=\frac{\text{volume to be added}}{\text{net discharge}}\]

Use litres/minute or cubic metres/hour consistently.

Partly filled tank

If fraction \(f\) is already filled, remaining work is:

\[W_{\text{left}}=1-f\]

Do not calculate from an empty tank unless stated.

03

The UPSC Trap / Watch Out

Protect accuracy when signs, schedules, efficiencies and units change.

Accuracy

AClassic distractors and reasoning errors

Adding times

Workers working together add rates, not completion times.

Efficiency ratio not reversed

If time ratio is \(2:3\), efficiency ratio is \(3:2\).

Outlet treated as positive

An emptying pipe or leak has a negative rate while the tank is filling.

Mixed time units

Convert hours to minutes or days to hours before combining rates.

Changing team ignored

Whenever someone joins or leaves, close the current phase and start a new rate.

Wrong alternate-day starter

The final fraction depends on whose turn begins the cycle and whose turn comes next.

Whole-day rounding

Do not round a fractional finishing day unless work is restricted to completed shifts.

Workers assumed identical

Men–days cancellation requires equal or explicitly adjusted efficiencies.

Hours per day omitted

When daily working hours change, include \(H\) in the production equation.

Different work quantities cancelled

If one job is larger, retain the work ratio \(W_1:W_2\).

Wages divided by time only

Wages follow work contribution, which depends on both efficiency and duration.

Leak time subtracted directly

Subtract rates \(\frac1x-\frac1y\), not hours \(y-x\).

Initial tank level ignored

A partly filled tank requires only the unfilled fraction.

Net rate sign not checked

If outlet capacity equals or exceeds inlet capacity, the tank will not fill.

Percent efficiency equals percent time

Inverse variation makes the percentage changes unequal.

Average rate used casually

Average rates require correct time weights; phase calculation is safer.

BHigh-speed shortcuts and mental methods

5 sec

Two helpers

For times \(x,y\), together time is \(\frac{xy}{x+y}\).

5 sec

Helper and destroyer

For positive time \(x\) and negative time \(y\), net time is \(\frac{xy}{y-x}\), with \(y\gt x\).

8 sec

LCM units

Choose total work as the LCM of individual times; rates become small integers.

8 sec

Efficiency reversal

Write time ratio, reverse it immediately, then label it efficiency.

10 sec

Pair-sum shortcut

Add the three pair rates and halve to obtain the rate of all three.

10 sec

Percent conversion

Efficiency rise \(x\%\) gives time fall \(\frac{100x}{100+x}\%\).

12 sec

Cycle block

Calculate work per full cycle first; handle only the residual separately.

12 sec

Contribution chart

For wages, write \(E\times T\) under each worker, reduce the ratio, then divide money.

15 sec

Direction check

Adding help must reduce time; adding a leak must increase filling time.

The safest exam sequence

Fix the total work, convert every agent to a signed rate, draw the schedule in phases, compute remaining work after each phase, and only then convert the final fraction into time.

04

Last-Minute Master Sheet

Compact relationships for rapid revision.

Revise
Work–rate–time\[W=RT,\quad R=\frac WT,\quad T=\frac WR\]
One-person rate\[T=x\Rightarrow R=\frac1x\]
Two helpers\[T=\frac{xy}{x+y}\]
One helper, one destroyer\[T=\frac{xy}{y-x},\quad y\gt x\]
Efficiency and time\[E_1:E_2=T_2:T_1\]
Workforce model\[W\propto MDHE\]
Wage ratio\[W_A:W_B=E_AT_A:E_BT_B\]
All three from pairs\[a+b+c=\frac{(a+b)+(b+c)+(c+a)}2\]
Net pipe rate\[R_{\text{net}}=\sum R_{\text{in}}-\sum R_{\text{out}}\]
Leak alone\[T_L=\frac{xy}{y-x}\]
Cycle work\[W_c=\sum R_iT_i\]
Partly filled tank\[W_{\text{left}}=1-f\]

QQuestion-type map

Single schedule?Add signed rates.
Team changes?Split into phases.
Pattern repeats?Use cycle work.
People/hours vary?Use \(MDHE\).

One-line memory rule

Time is obtained only after the relevant work is divided by the net signed rate for that phase.